ITAC Assessment: OR0292
ITAC logo
ITAC Assessment: OR0292
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Pumps
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 425
Plant Area 500,000
ft2
Annual Production 550
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $575,319 15,044,842
kWh
Electricity Demand $118,854 104,424
kW-mo/yr
Electricity Fees $11,863 -
Natural Gas $229,947 61,668
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $811,044 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $783,826

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 4.122: Develop standard procedures to improve internal yields $116,300 - - - - - - - $(-10,570.0)
-
lb
- $126,870 -
02 3.1175: Use a different or recycled raw material $17,850 - - - - - - $15,160
-
gal
- - $2,690 -
03 3.3123: Use decanting, flotation to remove contaminants $11,080 $2,000 $(-91.0)
(-2,638)
kWh
$(-16.0)
-
kW-mo/yr
- - - $6,492
-
gal
- $4,695 - -
04 3.3133: Use other waste concentration methods $6,602 $10,000 - $(-9.0)
-
kW-mo/yr
- $3,682
-
MMBtu
$(-10.0)
-
Tgal
$2,939
-
gal
- - - -
05 2.1232: Keep boiler tubes clean $7,179 $500 - - - $7,179
-
MMBtu
- - - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,202 $1,144 $1,121
32,532
kWh
$194
-
kW-mo/yr
- - - - - $394 - $493
07 2.7491: Insulate glazing, walls, ceilings, and roofs $12,370 $23,720 - - - $12,370
-
MMBtu
- - - - - -
08 2.3212: Optimize plant power factor $8,246 $28,000 - - $8,246 - - - - - - -
09 2.4133: Use most efficient type of electric motors $4,215 $23,353 $2,117
61,254
kWh
$2,098
-
kW-mo/yr
- - - - - - - -
10 4.112: Replace old machine with new automatic multi-station tool $250,000 - - - - - - - - $250,000 - -
11 4.425: Eliminate/reduce redundant inspections $375,000 - - - - - - - - $375,000 - -
TOTAL RECOMMENDED $811,044 $88,717 $3,147
91,148
kWh
$2,267
-
kW-mo/yr
$8,246 $23,231
-
MMBtu
$(-10.0)
-
Tgal
$24,591
-
gal
$(-10,570.0)
-
lb
$630,089 $129,560 $493
TOTAL IMPLEMENTED $783,826 $26,997 $3,147
91,148
kWh
$2,276
-
kW-mo/yr
- $7,179
-
MMBtu
- $21,652
-
gal
$(-10,570.0)
-
lb
$630,089 $129,560 $493
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs