Assessment Year | 1997 |
---|---|
Principal Product | Pumps |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 425 |
Plant Area |
500,000
ft2
|
Annual Production | 550
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $575,319 | 15,044,842 |
kWh
|
$0.038 |
Electricity Demand | $118,854 | 104,424 |
kW-mo/yr
|
$1.14 |
Electricity Fees | $11,863 | - |
|
- |
Natural Gas | $229,947 | 61,668 |
MMBtu
|
$3.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $811,044 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $783,826 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.122: Develop standard procedures to improve internal yields | $116,300 | - | - | - | - | - | - | - |
$(-10,570.0)
-
lb
|
- | $126,870 | - | |
02 | 3.1175: Use a different or recycled raw material | $17,850 | - | - | - | - | - | - |
$15,160
-
gal
|
- | - | $2,690 | - | |
03 | 3.3123: Use decanting, flotation to remove contaminants | $11,080 | $2,000 |
$(-91.0)
(-2,638)
kWh
|
$(-16.0)
-
kW-mo/yr
|
- | - | - |
$6,492
-
gal
|
- | $4,695 | - | - | |
04 | 3.3133: Use other waste concentration methods | $6,602 | $10,000 | - |
$(-9.0)
-
kW-mo/yr
|
- |
$3,682
-
MMBtu
|
$(-10.0)
-
Tgal
|
$2,939
-
gal
|
- | - | - | - | |
05 | 2.1232: Keep boiler tubes clean | $7,179 | $500 | - | - | - |
$7,179
-
MMBtu
|
- | - | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,202 | $1,144 |
$1,121
32,532
kWh
|
$194
-
kW-mo/yr
|
- | - | - | - | - | $394 | - | $493 | |
07 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $12,370 | $23,720 | - | - | - |
$12,370
-
MMBtu
|
- | - | - | - | - | - | |
08 | 2.3212: Optimize plant power factor | $8,246 | $28,000 | - | - | $8,246 | - | - | - | - | - | - | - | |
09 | 2.4133: Use most efficient type of electric motors | $4,215 | $23,353 |
$2,117
61,254
kWh
|
$2,098
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
10 | 4.112: Replace old machine with new automatic multi-station tool | $250,000 | - | - | - | - | - | - | - | - | $250,000 | - | - | |
11 | 4.425: Eliminate/reduce redundant inspections | $375,000 | - | - | - | - | - | - | - | - | $375,000 | - | - | |
TOTAL RECOMMENDED | $811,044 | $88,717 |
$3,147
91,148
kWh
|
$2,267
-
kW-mo/yr
|
$8,246 |
$23,231
-
MMBtu
|
$(-10.0)
-
Tgal
|
$24,591
-
gal
|
$(-10,570.0)
-
lb
|
$630,089 | $129,560 | $493 | ||
TOTAL IMPLEMENTED | $783,826 | $26,997 |
$3,147
91,148
kWh
|
$2,276
-
kW-mo/yr
|
- |
$7,179
-
MMBtu
|
- |
$21,652
-
gal
|
$(-10,570.0)
-
lb
|
$630,089 | $129,560 | $493 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs