ITAC Assessment: OR0108
ITAC logo
ITAC Assessment: OR0108
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product LAWN & GARDEN PRODUCTS
NAICS
n/a
SIC 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area
n/a
Annual Production 2,700,000
pieces
Production Hrs. Annual 2,268
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $29,803 617,233
kWh
Natural Gas $52,559 13,286
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,654 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,654

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $615 - $509
11,430
kWh
- $106
02 2.1233: Analyze flue gas for proper air/fuel ratio $1,129 $500 - $1,129
-
MMBtu
-
03 2.2511: Insulate bare equipment $2,482 $4,030 - $2,482
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $407 - $459
11,137
kWh
- $(-52.0)
05 2.4133: Use most efficient type of electric motors $21 $60 $21
586
kWh
- -
TOTAL RECOMMENDED $4,654 $4,590 $989
23,153
kWh
$3,611
-
MMBtu
$54
TOTAL IMPLEMENTED $4,654 $4,590 $989
23,153
kWh
$3,611
-
MMBtu
$54
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs