ITAC Assessment: OK1179
ITAC logo
ITAC Assessment: OK1179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Management services
NAICS 561110: Office Administrative Services
SIC 8741: Management Services
Sales Range $500
k
to 1
M
# of Employees 50
Plant Area 42,000
ft2
Annual Production 1
units
Production Hrs. Annual 2,600
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,566 596,720
kWh
Electricity Demand $15,542 1,905
kW-mo/yr
Natural Gas $5,189 497
MMBtu
Waste Disposal Costs
Water Usage $6,728 1,338
Tgal
Water Disposal $6,728 1,338
Tgal
TOTAL YEARLY COSTS $76,753
RECOMMENDED SAVINGS* $13,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,620 $18,584 $3,670
51,688
kWh
$1,950
-
kW-mo/yr
02 2.7135: Install occupancy sensors $886 $633 $886
12,485
kWh
-
03 2.7232: Replace existing hvac unit with high efficiency model $422 $1,815 $422
5,939
kWh
-
04 2.7211: Clean and maintain refrigerant condensers and towers $4,726 $10,910 $4,726
66,557
kWh
-
05 2.6211: Conserve energy by efficient use of vending machines $2,146 $1,120 $2,146
30,222
kWh
-
TOTAL RECOMMENDED $13,800 $33,062 $11,850
166,891
kWh
$1,950
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs