ITAC Assessment: OK1111
ITAC logo
ITAC Assessment: OK1111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Aerospace components
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 158
Plant Area 715,000
ft2
Annual Production 5,000
units
Production Hrs. Annual 2,040
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $997,777 12,873,600
kWh
Electricity Demand $334,977 32,810
kW-mo/yr
Natural Gas $102,024 19,323
MMBtu
Waste Disposal Costs
Water Usage $32,294 4,310
Tgal
Water Disposal $15,202 4,310
Tgal
TOTAL YEARLY COSTS $1,482,274
RECOMMENDED SAVINGS* $220,659 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $46,469 $113,104 $38,591
494,754
kWh
$7,878
-
kW-mo/yr
-
02 2.9114: Use solar heat to make electricty $129,812 $935,220 $129,812
1,664,250
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,271 $46,928 $31,271
400,908
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,608 $3,599 $3,608
46,255
kWh
- -
05 2.1212: Operate boilers on high fire setting $935 $22,000 - - $935
-
MMBtu
06 2.7135: Install occupancy sensors $83 $83 $83
1,058
kWh
- -
07 2.7211: Clean and maintain refrigerant condensers and towers $7,982 $16,792 $7,982
102,326
kWh
- -
08 2.6211: Conserve energy by efficient use of vending machines $499 $236 $499
6,390
kWh
- -
TOTAL RECOMMENDED $220,659 $1,137,962 $211,846
2,715,941
kWh
$7,878
-
kW-mo/yr
$935
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs