Assessment Year | 2001 |
---|---|
Principal Product | Aluminum Cans |
NAICS |
n/a
|
SIC | 3411: Metal Cans |
Sales Range | $50 M to 100M |
# of Employees | 77 |
Plant Area |
108,000
ft2
|
Annual Production | 1,100,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $490,943 | 18,771,200 |
kWh
|
$0.026 |
Electricity Demand | $193,086 | - |
|
- |
Electricity Fees | $203,904 | - |
|
- |
Natural Gas | $392,431 | 59,663 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,088 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $4,472 | $11,200 | n/a | - | - |
$4,472
-
MMBtu
|
- | - | - |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,077 | $15,842 | n/a |
$689
26,280
kWh
|
$235
-
kW-mo/yr
|
- | - | $3,153 | - |
03 | 2.7135: Install occupancy sensors | $534 | $1,045 | n/a |
$534
33,954
kWh
|
- | - | - | - | - |
04 | 2.2437: Recover waste heat from equipment | $25,294 | $2,457 | n/a |
$2,678
81,687
kWh
|
- |
$22,616
-
MMBtu
|
- | - | - |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $28,667 | $14,150 | n/a |
$21,402
816,870
kWh
|
$7,265
-
kW-mo/yr
|
- | - | - | - |
06 | 3.4111: Use closed cycle process to minimize waste water production | $3,044 | $2,350 | n/a | - | - |
$1,113
-
MMBtu
|
$919
-
Tgal
|
- |
$1,012
-
Tgal
|
TOTAL RECOMMENDED | $66,088 | $47,044 |
$25,303
958,791
kWh
|
$7,500
-
kW-mo/yr
|
$28,201
-
MMBtu
|
$919
-
Tgal
|
$3,153 |
$1,012
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs