Assessment Year | 2001 |
---|---|
Principal Product | Fiberglass & Vacuum Form Plastic |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 60 |
Plant Area |
72,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 4,368
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $89,813 | 1,504,240 |
kWh
|
$0.060 |
Electricity Fees | $233 | - |
|
- |
Natural Gas | $19,976 | 3,438 |
MMBtu
|
$5.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $111,894 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $64,586 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,536 | $13,800 |
$3,200
56,638
kWh
|
- | $336 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,000 | $300 |
$8,100
142,945
kWh
|
- | $(-100.0) | |
03 | 2.2437: Recover waste heat from equipment | $2,550 | $1,185 | - |
$2,550
-
MMBtu
|
- | |
04 | 4.445: Install equipment to move product | $50,500 | $25,810 | - | - | $50,500 | |
05 | 4.424: Improve space comfort conditioning | $47,308 | $16,792 |
$(-160.0)
(-2,820)
kWh
|
- | $47,468 | |
TOTAL RECOMMENDED | $111,894 | $57,887 |
$11,140
196,763
kWh
|
$2,550
-
MMBtu
|
$98,204 | ||
TOTAL IMPLEMENTED | $64,586 | $41,095 |
$11,300
199,583
kWh
|
$2,550
-
MMBtu
|
$50,736 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs