ITAC Assessment: OK0590
ITAC logo
ITAC Assessment: OK0590
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Structural Steel
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 55,000
ft2
Annual Production 6,480
ton
Production Hrs. Annual 2,720
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,842 542,204
kWh
Electricity Demand $37,526 9,168
kW-mo/yr
Electricity Fees $685 -
Natural Gas $10,075 2,194
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,504 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,635

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $17,680 $250 - - $17,680
02 4.111: Add equipment/ operators to reduce production bottleneck $5,824 $3,443 - - $5,824
03 3.6124: Burn waste oil for heat $2,892 $3,490 - $2,892
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,604 $5,081 $2,604
34,877
kWh
- -
05 2.2437: Recover waste heat from equipment $2,743 $1,613 $2,743
40,445
kWh
- -
06 2.7135: Install occupancy sensors $761 $1,440 $761
11,137
kWh
- -
TOTAL RECOMMENDED $32,504 $15,317 $6,108
86,459
kWh
$2,892
-
MMBtu
$23,504
TOTAL IMPLEMENTED $5,635 $5,103 $2,743
40,445
kWh
$2,892
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs