ITAC Assessment: OK0538
ITAC logo
ITAC Assessment: OK0538
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Biscotti-cookies
NAICS
n/a
SIC 2052: Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 56,000
ft2
Annual Production 4,500,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,304 1,059,496
kWh
Electricity Fees $1,191 -
Natural Gas $24,810 4,405
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $171,441 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,881

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4239: Eliminate or reduce compressed air usage $4,000 $1,600 $4,000
43,669
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $760 $1,000 $599
8,206
kWh
- $161 -
03 4.821: Pay bills on time to avoid late fees $651 - - - - $651
04 3.1191: Change procedures / equipment / operating conditions $87,640 $100,000 - $540
-
lb
$87,100 -
05 4.452: Eliminate shift $49,920 - - - $49,920 -
06 3.5317: Sell / offer by-product as animal feed $28,470 - - $28,470
-
lb
- -
TOTAL RECOMMENDED $171,441 $102,600 $4,599
51,875
kWh
$29,010
-
lb
$137,181 $651
TOTAL IMPLEMENTED $33,881 $2,600 $4,599
51,875
kWh
$28,470
-
lb
$161 $651
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs