ITAC Assessment: OK0438
ITAC logo
ITAC Assessment: OK0438
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Progressive cavity pumps
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $5
M
to 10
M
# of Employees 62
Plant Area 37,202
ft2
Annual Production 420
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,782 1,309,203
kWh
Natural Gas $9,613 2,628
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,812 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,227

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $5,195 $1,030 - $5,195
-
MMBtu
02 2.2441: Preheat boiler makeup water with waste process heat $893 $1,145 - $893
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $397 $800 $397
14,947
kWh
-
04 2.7135: Install occupancy sensors $203 $280 $203
4,982
kWh
-
05 2.2511: Insulate bare equipment $32 $92 - $32
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $92 $280 $92
1,172
kWh
-
TOTAL RECOMMENDED $6,812 $3,627 $692
21,101
kWh
$6,120
-
MMBtu
TOTAL IMPLEMENTED $5,227 $1,122 - $5,227
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs