Assessment Year | 1994 |
---|---|
Principal Product | Progressive cavity pumps |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $5 M to 10M |
# of Employees | 62 |
Plant Area |
37,202
ft2
|
Annual Production | 420
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $92,782 | 1,309,203 |
kWh
|
$0.071 |
Natural Gas | $9,613 | 2,628 |
MMBtu
|
$3.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,812 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,227 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $5,195 | $1,030 | - |
$5,195
-
MMBtu
|
|
02 | 2.2441: Preheat boiler makeup water with waste process heat | $893 | $1,145 | - |
$893
-
MMBtu
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $397 | $800 |
$397
14,947
kWh
|
- | |
04 | 2.7135: Install occupancy sensors | $203 | $280 |
$203
4,982
kWh
|
- | |
05 | 2.2511: Insulate bare equipment | $32 | $92 | - |
$32
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $92 | $280 |
$92
1,172
kWh
|
- | |
TOTAL RECOMMENDED | $6,812 | $3,627 |
$692
21,101
kWh
|
$6,120
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,227 | $1,122 | - |
$5,227
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs