ITAC Assessment: OD0108
ITAC logo
ITAC Assessment: OD0108
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Glass Figurines
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 61,000
ft2
Annual Production 700,000
pieces
Production Hrs. Annual 2,808
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,982 1,103,165
kWh
Electricity Demand $24,521 5,185
kW-mo/yr
Electricity Fees $3,853 -
Natural Gas $13,442 1,936
MMBtu
LPG $36,066 3,356
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $76,874 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,177

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings By-product Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,767 $8,940 $3,404
59,496
kWh
$1,363
-
kW-mo/yr
- - - -
02 2.1332: Convert combustion equipment to burn natural gas $61,697 - - - $25,631
-
MMBtu
$36,066
-
MMBtu
- -
03 2.7224: Reduce space conditioning during non-working hours $218 $78 - - $218
-
MMBtu
- - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $4,965 $10,000 - - - - $4,965
-
lb
-
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,227 $2,760 - - - - - $5,227
TOTAL RECOMMENDED $76,874 $21,778 $3,404
59,496
kWh
$1,363
-
kW-mo/yr
$25,849
-
MMBtu
$36,066
-
MMBtu
$4,965
-
lb
$5,227
TOTAL IMPLEMENTED $15,177 $21,778 $3,404
59,496
kWh
$1,363
-
kW-mo/yr
$218
-
MMBtu
- $4,965
-
lb
$5,227
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs