ITAC Assessment: OD0098
ITAC logo
ITAC Assessment: OD0098
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Metalworking
NAICS
n/a
SIC 3549: Metalworking Machinery, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 53
Plant Area 70,000
ft2
Annual Production 55,000
ton
Production Hrs. Annual 2,340
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,999 1,065,944
kWh
Electricity Demand $37,201 4,631
kW-mo/yr
Electricity Fees $134 -
Fuel Oil #4 $24,000 5,560
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,852 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $488

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,576 $2,296 $852
22,860
kWh
$724
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $992 $789 $992
26,377
kWh
- - -
03 2.7221: Lower temperature during the winter season and vice-versa $488 $40,000 $488
12,896
kWh
- - -
04 3.6192: Use a less expensive method of waste removal $421 - - - $421
-
gal
-
05 3.5313: Increase amount of waste recovered for resale $1,375 - - - - $1,375
-
lb
TOTAL RECOMMENDED $4,852 $43,085 $2,332
62,133
kWh
$724
-
kW-mo/yr
$421
-
gal
$1,375
-
lb
TOTAL IMPLEMENTED $488 $40,000 $488
12,896
kWh
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs