ITAC Assessment: OD0090
ITAC logo
ITAC Assessment: OD0090
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Wooden Doors
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $500
k
to 1
M
# of Employees 21
Plant Area 8,000
ft2
Annual Production 18,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $6,429 140,387
kWh
Electricity Demand $5,052 557
kW-mo/yr
Electricity Fees $1,167 -
LPG $1,326 119
MMBtu
Fuel Oil #4 $2,683 362
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,822 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $877

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #2 Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $863 $1,657 $451
55,393
kWh
$412
-
kW-mo/yr
- - -
02 2.1331: Burn a less expensive grade of fuel $877 $688 - - $2,666
-
MMBtu
$(-1,789.0)
-
MMBtu
-
03 3.5313: Increase amount of waste recovered for resale $1,082 - - - - - $1,082
-
lb
TOTAL RECOMMENDED $2,822 $2,345 $451
55,393
kWh
$412
-
kW-mo/yr
$2,666
-
MMBtu
$(-1,789.0)
-
MMBtu
$1,082
-
lb
TOTAL IMPLEMENTED $877 $688 - - $2,666
-
MMBtu
$(-1,789.0)
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs