Assessment Year | 1996 |
---|---|
Principal Product | Prestressed Concrete Structures |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $5 M to 10M |
# of Employees | 85 |
Plant Area |
100,000
ft2
|
Annual Production | 27,000
pieces
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,991 | 624,267 |
kWh
|
$0.050 |
Electricity Demand | $8,150 | 1,691 |
kW-mo/yr
|
$4.82 |
Electricity Fees | $353 | - |
|
- |
Natural Gas | $19,039 | 4,290 |
MMBtu
|
$4.44 |
Fuel Oil #2 | $1,452 | 144 |
MMBtu
|
$10.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $111,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,986 | $800 | n/a |
$1,986
45,428
kWh
|
- | - | - | - | - | - |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $579 | $20 | n/a |
$579
13,189
kWh
|
- | - | - | - | - | - |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,247 | $1,602 | n/a |
$1,652
33,411
kWh
|
$595
-
kW-mo/yr
|
- | - | - | - | - |
04 | 2.4133: Use most efficient type of electric motors | $239 | $373 | n/a |
$151
2,931
kWh
|
$88
-
kW-mo/yr
|
- | - | - | - | - |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $879 | $1,495 | n/a | - | - |
$879
-
MMBtu
|
- | - | - | - |
06 | 3.5311: Recover and reuse waste material | $104,960 | $2,400 | n/a | - | - | - | - | $(-12,960.0) | $(-5,280.0) | $123,200 |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $372 | - | n/a | - | - | - |
$372
-
lb
|
- | - | - |
TOTAL RECOMMENDED | $111,262 | $6,690 |
$4,368
94,959
kWh
|
$683
-
kW-mo/yr
|
$879
-
MMBtu
|
$372
-
lb
|
$(-12,960.0) | $(-5,280.0) | $123,200 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs