Assessment Year | 2000 |
---|---|
Principal Product | Commercial Printing,Lithographic |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $5 M to 10M |
# of Employees | 38 |
Plant Area |
7,200
ft2
|
Annual Production | 5
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,018 | 921,747 |
kWh
|
$0.059 |
Electricity Demand | $22,257 | 3,269 |
kW-mo/yr
|
$6.81 |
Electricity Fees | $7,330 | - |
|
- |
LPG | $2,116 | 158 |
MMBtu
|
$13.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,791 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,986 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $1,583 | - |
$649
11,430
kWh
|
- | $934 | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $357 | $100 |
$229
3,810
kWh
|
$102
-
kW-mo/yr
|
$26 | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $385 | $3,344 |
$249
4,396
kWh
|
$56
-
kW-mo/yr
|
$80 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $359 | $105 |
$289
3,810
kWh
|
$49
-
kW-mo/yr
|
$21 | - | |
05 | 2.7241: Install outside air damper / economizer on hvac unit | $13,222 | $10,869 |
$9,767
166,764
kWh
|
$2,502
-
kW-mo/yr
|
$953 | - | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $885 | $304 |
$49
879
kWh
|
$8
-
kW-mo/yr
|
$4 |
$824
-
MMBtu
|
|
TOTAL RECOMMENDED | $16,791 | $14,722 |
$11,232
191,089
kWh
|
$2,717
-
kW-mo/yr
|
$2,018 |
$824
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,986 | $3,853 |
$816
12,895
kWh
|
$215
-
kW-mo/yr
|
$131 |
$824
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs