| Assessment Year | 1998 |
|---|---|
| Principal Product | Asphalt Paving Mixtures |
| NAICS |
n/a
|
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $1 M to 5M |
| # of Employees | 14 |
| Plant Area |
n/a
|
| Annual Production | 375,000
ton
|
| Production Hrs. Annual | 1,190
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,717 | 1,611,958 |
kWh
|
$0.041 |
| Electricity Demand | $108,635 | 11,719 |
kW-mo/yr
|
$9.27 |
| Electricity Fees | $4,522 | - |
|
- |
| LPG | $198,222 | 37,346 |
MMBtu
|
$5.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,700 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $5,521 | $33,286 |
$1,691
41,032
kWh
|
$3,824
-
kW-mo/yr
|
$6 | - | - | |
| 02 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $5,867 | $30,000 | - | - | - |
$5,867
-
MMBtu
|
- | |
| 03 | 2.2511: Insulate bare equipment | $179 | $436 | - | - | - |
$179
-
MMBtu
|
- | |
| 04 | 2.7134: Use photocell controls | $775 | $290 |
$479
11,430
kWh
|
$294
-
kW-mo/yr
|
$2 | - | - | |
| 05 | 3.5311: Recover and reuse waste material | $(-536.0) | - | - | - | - | - | $(-536.0) | |
| TOTAL RECOMMENDED | $11,806 | $64,012 |
$2,170
52,462
kWh
|
$4,118
-
kW-mo/yr
|
$8 |
$6,046
-
MMBtu
|
$(-536.0) | ||
| TOTAL IMPLEMENTED | $5,700 | $33,722 |
$1,691
41,032
kWh
|
$3,824
-
kW-mo/yr
|
$6 |
$179
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs