| Assessment Year | 2026 |
|---|---|
| Principal Product | Breakfast Cereals |
| NAICS | 311230: Breakfast Cereal Manufacturing |
| SIC | 2043: Cereal Breakfast Foods |
| Sales Range | $100 M to 500M |
| # of Employees | 45 |
| Plant Area |
58,458
ft2
|
| Annual Production | 5,200,000
lb
|
| Production Hrs. Annual | 2,100
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $42,872 | 454,900 |
kWh
|
$0.094 | |
| Electricity Demand | $21,228 | 1,687 |
kW-mo/yr
|
$12.58 | |
| Electricity Fees | $9,059 | - |
|
- | |
| Natural Gas | $5,960 | 608 |
MMBtu
|
$9.81 | |
| Fuel Oil #2 | $4,525 | 173 |
MMBtu
|
$26.10 | |
| Other Gas | $1,302 | 1 |
MMBtu
|
$1,302.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,713 | 237 |
Tgal
|
$11.43 | |
| Water Disposal | $3,236 | 237 |
Tgal
|
$13.64 | |
| Other Liquid (non-haz) | $1,993 | 1 |
gal
|
$1,993.00 | |
| TOTAL YEARLY COSTS | $92,888 | ||||
| RECOMMENDED SAVINGS* | $638,318 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Gas Savings | Water Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.441: Install automatic packing equipment | $150,000 | $120,000 | - | - | - | - | - | - | - | - | - | - | $105,000 | - | $45,000 | |
| 02 | 2.8212: Reduce delivery schedules | $150,000 | $756,600 |
$(-1,473.0)
(-15,666)
kWh
|
- | - | - | - | - | - | - | - | $95,473 | - | $56,000 | - | |
| 03 | 4.512: Condense operation into one building | $150,000 | $700,000 | - | - | - | - |
$4,131
-
MMBtu
|
- | - | - | - | - | - | $145,869 | - | |
| 04 | 2.4131: Size electric motors for peak operating efficiency | $150,000 | $321,746 | - | - | - | - | - | - |
$36
-
Tgal
|
$43
-
Tgal
|
- | $10,000 | - | - | $139,921 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,373 | $17,082 |
$9,967
106,037
kWh
|
$3,374
-
kW-mo/yr
|
- | - | - | - | - | - | - | $1,032 | - | - | - | |
| 06 | 3.5311: Recover and reuse waste material | $11,535 | $280 | - | - | - | - |
$394
-
MMBtu
|
- | - | - | - | - | - | $11,141 | - | |
| 07 | 2.8121: Apply for tax-free status for energy purchases | $4,191 | $2,080 | - | - | $4,076 | - | - |
$4
-
MMBtu
|
- | - |
$111
-
gal
|
- | - | - | - | |
| 08 | 2.7492: Use proper thickness of insulation on building envelope | $3,842 | $6,104 |
$220
2,339
kWh
|
- | - |
$3,622
-
MMBtu
|
- | - | - | - | - | - | - | - | - | |
| 09 | 2.7135: Install occupancy sensors | $3,379 | $2,454 |
$3,379
35,948
kWh
|
- | - | - | - | - | - | - | - | - | - | - | - | |
| 10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $390 | $100 |
$380
4,043
kWh
|
- | - | - | - | - | - | - | - | $(-160.0) | $(-100.0) | $270 | - | |
| 11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $374 | $40 |
$374
3,981
kWh
|
- | - | - | - | - | - | - | - | - | - | - | - | |
| 12 | 2.4239: Eliminate or reduce compressed air usage | $234 | $129 |
$234
2,488
kWh
|
- | - | - | - | - | - | - | - | - | - | - | - | |
| TOTAL RECOMMENDED | $638,318 | $1,926,615 |
$13,081
139,170
kWh
|
$3,374
-
kW-mo/yr
|
$4,076 |
$3,622
-
MMBtu
|
$4,525
-
MMBtu
|
$4
-
MMBtu
|
$36
-
Tgal
|
$43
-
Tgal
|
$111
-
gal
|
$106,345 | $104,900 | $213,280 | $184,921 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Gas Savings | Water Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs