ITAC Assessment: NC0448
ITAC logo
ITAC Assessment: NC0448
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Potato chips
NAICS 311919: Other Snack Food Manufacturing
SIC 2096: Potato Chips, Corn Chips, and Similar Snacks
Sales Range $100
M
to 500
M
# of Employees 220
Plant Area 106,000
ft2
Annual Production 40,000,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $281,386 4,205,440
kWh
Electricity Demand $94,806 8,218
kW-mo/yr
Natural Gas $757,168 177,285
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,768 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,366

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.212: Adopt in-house material generation $42,880 $75,000 $(-8,830.0)
(-132,000)
kWh
$(-2,770.0)
-
kW-mo/yr
- - $(-2,400.0) $56,880
02 2.2437: Recover waste heat from equipment $19,522 $100,000 - - $19,522
-
MMBtu
- - -
03 2.2437: Recover waste heat from equipment $2,746 $5,600 - - $2,746
-
MMBtu
- - -
04 2.7111: Reduce illumination to minimum necessary levels $1,740 $400 $1,325
19,800
kWh
$415
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $880 $200 $989
14,784
kWh
$311
-
kW-mo/yr
- $(-300.0) - $(-120.0)
TOTAL RECOMMENDED $67,768 $181,200 $(-6,516.0)
(-97,416)
kWh
$(-2,044.0)
-
kW-mo/yr
$22,268
-
MMBtu
$(-300.0) $(-2,400.0) $56,760
TOTAL IMPLEMENTED $5,366 $6,200 $2,314
34,584
kWh
$726
-
kW-mo/yr
$2,746
-
MMBtu
$(-300.0) - $(-120.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs