ITAC Assessment: NC0352
ITAC logo
ITAC Assessment: NC0352
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Bricks
NAICS 327120: Clay Building Material and Refractories Manufacturing
SIC 3251: Brick and Structural Clay Tile
Sales Range $5
M
to 10
M
# of Employees 114
Plant Area 200,000
ft2
Annual Production 160,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $480,953 11,078,300
kWh
Electricity Demand $165,300 34,800
kW-mo/yr
Electricity Fees $9,418 -
Natural Gas $4,512,828 461,477
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,732 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,968

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7124: Make a practice of turning off lights when not needed $28,336 $8,000 $28,336
652,921
kWh
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,199 $1,371 $1,043
24,027
kWh
$156
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,127 $50 $4,456
102,667
kWh
$671
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $784 $1,000 $399
9,198
kWh
$60
-
kW-mo/yr
- $210 $115
05 2.2437: Recover waste heat from equipment $1,565 $4,000 - - $1,565
-
MMBtu
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $721 $100 $1,671
38,491
kWh
$250
-
kW-mo/yr
- $(-600.0) $(-600.0)
TOTAL RECOMMENDED $37,732 $14,521 $35,905
827,304
kWh
$1,137
-
kW-mo/yr
$1,565
-
MMBtu
$(-390.0) $(-485.0)
TOTAL IMPLEMENTED $34,968 $9,150 $34,862
803,277
kWh
$981
-
kW-mo/yr
- $(-390.0) $(-485.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs