| Assessment Year | 2007 |
|---|---|
| Principal Product | Bricks |
| NAICS | 327120: Clay Building Material and Refractories Manufacturing |
| SIC | 3251: Brick and Structural Clay Tile |
| Sales Range | $5 M to 10M |
| # of Employees | 114 |
| Plant Area |
200,000
ft2
|
| Annual Production | 160,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $480,953 | 11,078,300 |
kWh
|
$0.043 |
| Electricity Demand | $165,300 | 34,800 |
kW-mo/yr
|
$4.75 |
| Electricity Fees | $9,418 | - |
|
- |
| Natural Gas | $4,512,828 | 461,477 |
MMBtu
|
$9.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $37,732 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,968 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7124: Make a practice of turning off lights when not needed | $28,336 | $8,000 |
$28,336
652,921
kWh
|
- | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,199 | $1,371 |
$1,043
24,027
kWh
|
$156
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,127 | $50 |
$4,456
102,667
kWh
|
$671
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $784 | $1,000 |
$399
9,198
kWh
|
$60
-
kW-mo/yr
|
- | $210 | $115 | |
| 05 | 2.2437: Recover waste heat from equipment | $1,565 | $4,000 | - | - |
$1,565
-
MMBtu
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $721 | $100 |
$1,671
38,491
kWh
|
$250
-
kW-mo/yr
|
- | $(-600.0) | $(-600.0) | |
| TOTAL RECOMMENDED | $37,732 | $14,521 |
$35,905
827,304
kWh
|
$1,137
-
kW-mo/yr
|
$1,565
-
MMBtu
|
$(-390.0) | $(-485.0) | ||
| TOTAL IMPLEMENTED | $34,968 | $9,150 |
$34,862
803,277
kWh
|
$981
-
kW-mo/yr
|
- | $(-390.0) | $(-485.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs