ITAC Assessment: NC0334
ITAC logo
ITAC Assessment: NC0334
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Industrial controllers and meters
NAICS 334514: Totalizing Fluid Meter and Counting Device Manufacturing
SIC 3690:
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 166,400
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $515,895 10,409,500
kWh
Electricity Demand $101,736 20,805
kW-mo/yr
Electricity Fees $19,004 -
LPG $146,590 13,631
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $69,746 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,208

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.2121: Increase amount of condensate returned $12,388 $7,290 - - $8,708
-
MMBtu
$(-500.0) - $4,180
-
Tgal
02 2.1133: Adjust burners for efficient operation $2,870 $1,000 - - $2,870
-
MMBtu
- - -
03 2.6218: Turn off equipment when not in use $8,466 $500 - - $8,466
-
MMBtu
- - -
04 3.4115: Recover and reuse cooling water $1,680 $620 - - - - - $1,680
-
Tgal
05 2.7314: Reduce ventilation air $10,892 $4,000 $8,912
210,628
kWh
$1,980
-
kW-mo/yr
- - - -
06 2.7211: Clean and maintain refrigerant condensers and towers $3,773 $1,300 $2,733
64,606
kWh
$1,040
-
kW-mo/yr
- - - -
07 2.6218: Turn off equipment when not in use $6,065 - $4,929
116,508
kWh
$1,796
-
kW-mo/yr
- $(-640.0) $(-20.0) -
08 2.7241: Install outside air damper / economizer on hvac unit $3,306 $8,000 $3,306
78,133
kWh
- - - - -
09 2.2511: Insulate bare equipment $5,061 $3,300 $3,279
77,497
kWh
$1,782
-
kW-mo/yr
- - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,095 $100 $1,663
39,312
kWh
$632
-
kW-mo/yr
- $(-900.0) $(-300.0) -
11 2.2437: Recover waste heat from equipment $9,138 $9,824 - - $9,138
-
MMBtu
- - -
12 3.3122: Use filtration, centrifuging to remove contaminants $5,012 $4,200 - - - - $5,012 -
TOTAL RECOMMENDED $69,746 $40,134 $24,822
586,684
kWh
$7,230
-
kW-mo/yr
$29,182
-
MMBtu
$(-2,040.0) $4,692 $5,860
-
Tgal
TOTAL IMPLEMENTED $43,208 $18,820 $24,822
586,684
kWh
$7,230
-
kW-mo/yr
$11,336
-
MMBtu
$(-1,540.0) $(-320.0) $1,680
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs