| Assessment Year | 1997 |
|---|---|
| Principal Product | Canned meats |
| NAICS |
n/a
|
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $10 M to 50M |
| # of Employees | 175 |
| Plant Area |
120,000
ft2
|
| Annual Production | 50,000,000
lb
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $54,274 | 2,081,477 |
kWh
|
$0.026 |
| Electricity Demand | $59,711 | 6,058 |
kW-mo/yr
|
$9.86 |
| Electricity Fees | $1,984 | - |
|
- |
| Fuel Oil #2 | $251,594 | 48,113 |
MMBtu
|
$5.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $214,304 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $161,204 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $92 | $140 |
$25
879
kWh
|
$67
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $445 | $1,260 |
$136
5,275
kWh
|
$309
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $799 | $700 | - | - |
$799
-
MMBtu
|
- | - | - | - | |
| 04 | 2.2444: Use hot process fluids to preheat incoming process fluids | $28,209 | $17,238 | - | - |
$28,209
-
MMBtu
|
- | - | - | - | |
| 05 | 2.2628: Utilize a less expensive cooling method | $18,878 | $49,000 |
$6,188
237,397
kWh
|
$5,914
-
kW-mo/yr
|
$6,776
-
MMBtu
|
- | - | - | - | |
| 06 | 2.2511: Insulate bare equipment | $1,956 | $3,655 | - | - |
$1,956
-
MMBtu
|
- | - | - | - | |
| 07 | 2.7229: Air condition only space necessary | $3,389 | $7,155 |
$1,733
66,530
kWh
|
$1,656
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 2.1212: Operate boilers on high fire setting | $19,152 | $2,000 | - | - |
$19,152
-
MMBtu
|
- | - | - | - | |
| 09 | 3.1192: Reduce scrap production | $1,288 | $250 | - | - | - |
$38
-
lb
|
- | $1,250 | - | |
| 10 | 3.1191: Change procedures / equipment / operating conditions | $96 | $4,200 | - | - | - | - | - | - | $96 | |
| 11 | 4.441: Install automatic packing equipment | $140,000 | $300,000 | - | - | - | - | $140,000 | - | - | |
| TOTAL RECOMMENDED | $214,304 | $385,598 |
$8,082
310,081
kWh
|
$7,946
-
kW-mo/yr
|
$56,892
-
MMBtu
|
$38
-
lb
|
$140,000 | $1,250 | $96 | ||
| TOTAL IMPLEMENTED | $161,204 | $309,855 | - | - |
$21,108
-
MMBtu
|
- | $140,000 | - | $96 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs