ITAC Assessment: NC0064
ITAC logo
ITAC Assessment: NC0064
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Insulated wire and cable
NAICS
n/a
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 320
Plant Area 250,000
ft2
Annual Production 25,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $371,302 7,646,542
kWh
Natural Gas $47,911 7,468
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,871 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $221 $250 $221
1,465
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,813 $5,700 $1,813
36,342
kWh
03 2.7144: Install spectral reflectors / delamp $398 $560 $398
7,913
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,568 $780 $7,568
151,524
kWh
05 2.7241: Install outside air damper / economizer on hvac unit $277 $750 $277
5,569
kWh
06 2.2511: Insulate bare equipment $2,830 $278 $2,830
56,565
kWh
07 2.4239: Eliminate or reduce compressed air usage $2,764 $1,570 $2,764
55,393
kWh
TOTAL RECOMMENDED $15,871 $9,888 $15,871
314,771
kWh
TOTAL IMPLEMENTED $10,000 $7,290 $10,000
197,244
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs