ITAC Assessment: MZ1005
ITAC logo
ITAC Assessment: MZ1005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Research on polymer sheet, roll stock
NAICS 326130: Laminated Plastics Plate, Sheet (except Packaging), and Shape Manufacturing
SIC 8731: Commercial Physical and Biological Research
Sales Range less than $500
k
# of Employees 32
Plant Area 103,000
ft2
Annual Production 1
pieces
Production Hrs. Annual 1,992
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,207 1,082,320
kWh
Electricity Demand $29,114 6,882
kW-mo/yr
Natural Gas $12,861 1,150
MMBtu
Waste Disposal Costs
Water Usage $8,635 1,003
Tgal
Water Disposal $9,454 1,031
Tgal
TOTAL YEARLY COSTS $157,271
RECOMMENDED SAVINGS* $34,110 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Usage Savings Water Disposal Savings
01 2.7232: Replace existing hvac unit with high efficiency model $17,664 $184,235 $15,473
171,924
kWh
$2,191
-
kW-mo/yr
- -
02 2.7135: Install occupancy sensors $1,143 $1,200 $1,143
12,699
kWh
- - -
03 2.4239: Eliminate or reduce compressed air usage $478 $196 $224
2,485
kWh
$254
-
kW-mo/yr
- -
04 3.4159: Replace treated water with well / surface water $14,825 $110,000 - - $7,179
-
Tgal
$7,646
-
Tgal
TOTAL RECOMMENDED $34,110 $295,631 $16,840
187,108
kWh
$2,445
-
kW-mo/yr
$7,179
-
Tgal
$7,646
-
Tgal
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs