| Assessment Year | 2026 |
|---|---|
| Principal Product | cake, brownie, cookie dry mixes |
| NAICS | 311999: All Other Miscellaneous Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 165 |
| Plant Area |
342,000
ft2
|
| Annual Production | 162,000,000
lb
|
| Production Hrs. Annual | 6,960
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,034,324 | 28,692,542 |
kWh
|
$0.036 |
| Electricity Demand | $308,935 | 55,570 |
kW-mo/yr
|
$5.56 |
| Natural Gas | $115,425 | 35,367 |
MMBtu
|
$3.26 |
| TOTAL YEARLY COSTS | $1,458,684 | |||
| RECOMMENDED SAVINGS* | $67,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,516 | $17,100 |
$23,516
653,220
kWh
|
- | - | |
| 02 | 2.2625: Chill water to the highest temperature possible | $8,616 | $19,492 |
$6,878
191,077
kWh
|
$1,738
-
kW-mo/yr
|
- | |
| 03 | 2.2625: Chill water to the highest temperature possible | $9,218 | $13,460 |
$7,280
202,213
kWh
|
$1,938
-
kW-mo/yr
|
- | |
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,996 | $1,600 | - | - |
$7,996
-
MMBtu
|
|
| 05 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $11,755 | $46,600 | - | - |
$11,755
-
MMBtu
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,595 | $1,000 |
$3,442
95,623
kWh
|
$153
-
kW-mo/yr
|
- | |
| 07 | 2.7135: Install occupancy sensors | $196 | $725 |
$196
5,457
kWh
|
- | - | |
| 08 | 2.4322: Use or replace with energy efficient substitutes | $2,878 | $1,700 |
$2,878
79,938
kWh
|
- | - | |
| TOTAL RECOMMENDED | $67,770 | $101,677 |
$44,190
1,227,528
kWh
|
$3,829
-
kW-mo/yr
|
$19,751
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs