| Assessment Year | 2014 |
|---|---|
| Principal Product | Liquid Cell culture media and buffers |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $50 M to 100M |
| # of Employees | 24 |
| Plant Area |
98,000
ft2
|
| Annual Production | 678,000
pieces
|
| Production Hrs. Annual | 5,760
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $625,711 | 9,801,955 |
kWh
|
$0.064 |
| Electricity Demand | $53,948 | 20,067 |
kW-mo/yr
|
$2.69 |
| Natural Gas | $227,159 | 45,734 |
MMBtu
|
$4.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $99,426 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,244 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $18,116 | $16,400 |
$18,116
283,773
kWh
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $4,128 | $6,040 |
$4,128
64,656
kWh
|
- | - | |
| 03 | 2.7292: Lower ceiling to reduce conditioned space | $9,091 | $25,000 |
$8,961
138,341
kWh
|
$130
-
kW-mo/yr
|
- | |
| 04 | 2.7292: Lower ceiling to reduce conditioned space | $6,580 | $25,750 |
$6,485
101,589
kWh
|
$95
-
kW-mo/yr
|
- | |
| 05 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $14,550 | $28,000 | - | - |
$14,550
-
MMBtu
|
|
| 06 | 2.7229: Air condition only space necessary | $46,961 | $5,500 |
$44,355
694,781
kWh
|
$2,606
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $99,426 | $106,690 |
$82,045
1,283,140
kWh
|
$2,831
-
kW-mo/yr
|
$14,550
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $22,244 | $22,440 |
$22,244
348,429
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs