| Assessment Year | 2014 |
|---|---|
| Principal Product | cement |
| NAICS | 327310: Cement Manufacturing |
| SIC | 3241: Cement, Hydraulic |
| Sales Range | $100 M to 500M |
| # of Employees | 105 |
| Plant Area |
2,000,000
ft2
|
| Annual Production | 2,100,000
ton
|
| Production Hrs. Annual | 8,700
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $8,011,619 | 221,935,612 |
kWh
|
$0.036 |
| Electricity Demand | $4,662,123 | 402,323 |
kW-mo/yr
|
$11.59 |
| Natural Gas | $334,000 | 85,000 |
MMBtu
|
$3.93 |
| Coal | $8,000,000 | 5,003,800 |
MMBtu
|
$1.60 |
| Other Energy | $260,000 | 9,466 |
MMBtu
|
$27.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,565,723 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $5,306,536 | $18,000,000 |
$3,664,980
101,523,000
kWh
|
$1,641,556
-
kW-mo/yr
|
- | - | |
| 02 | 3.1161: Eliminate/reduce an operation | $218,015 | - |
$150,573
4,171,000
kWh
|
$67,442
-
kW-mo/yr
|
- | - | |
| 03 | 2.2511: Insulate bare equipment | $66,528 | $339,300 |
$45,948
1,272,800
kWh
|
$20,580
-
kW-mo/yr
|
- | - | |
| 04 | 4.445: Install equipment to move product | $974,644 | $3,131,120 |
$(-70,771.0)
(-1,960,488)
kWh
|
$(-31,125.0)
-
kW-mo/yr
|
$230,736
-
MMBtu
|
$845,804 | |
| TOTAL RECOMMENDED | $6,565,723 | $21,470,420 |
$3,790,730
105,006,312
kWh
|
$1,698,453
-
kW-mo/yr
|
$230,736
-
MMBtu
|
$845,804 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs