| Assessment Year | 2025 |
|---|---|
| Principal Product | Mattresses |
| NAICS | 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing |
| SIC | 3086: Plastics Foam Products |
| Sales Range | $100 M to 500M |
| # of Employees | 405 |
| Plant Area |
303,200
ft2
|
| Annual Production | 228,789,000
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $506,336 | 5,648,400 |
kWh
|
$0.090 | |
| Electricity Demand | $145,115 | 10,776 |
kW-mo/yr
|
$13.47 | |
| Natural Gas | $49,504 | 63,869 |
MMBtu
|
$0.78 | |
| Waste Disposal Costs | |||||
| Water Usage | $10,420 | 11,035 |
Tgal
|
$0.94 | |
| TOTAL YEARLY COSTS | $711,374 | ||||
| RECOMMENDED SAVINGS* | $133,643 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $12,227 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $1,314 | $1,810 | - | - | $1,314 | |
| 02 | 2.9114: Use solar heat to make electricty | $121,416 | $769,370 |
$95,862
1,069,466
kWh
|
$25,554
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $2,676 | $7,542 |
$2,475
27,496
kWh
|
$202
-
kW-mo/yr
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,650 | - |
$7,650
85,379
kWh
|
- | - | |
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $586 | $8,100 |
$537
5,990
kWh
|
$49
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $133,643 | $786,822 |
$106,524
1,188,330
kWh
|
$25,805
-
kW-mo/yr
|
$1,314 | ||
| TOTAL IMPLEMENTED | $12,227 | $17,452 |
$10,662
118,864
kWh
|
$251
-
kW-mo/yr
|
$1,314 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs