ITAC Assessment: MS0439
ITAC logo
ITAC Assessment: MS0439
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Mattresses
NAICS 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $100
M
to 500
M
# of Employees 405
Plant Area 303,200
ft2
Annual Production 228,789,000
units
Production Hrs. Annual 8,400
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $506,336 5,648,400
kWh
Electricity Demand $145,115 10,776
kW-mo/yr
Natural Gas $49,504 63,869
MMBtu
Waste Disposal Costs
Water Usage $10,420 11,035
Tgal
TOTAL YEARLY COSTS $711,374
RECOMMENDED SAVINGS* $133,643 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.3212: Optimize plant power factor $1,314 $1,810 - - $1,314
02 2.9114: Use solar heat to make electricty $121,416 $769,370 $95,862
1,069,466
kWh
$25,554
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $2,676 $7,542 $2,475
27,496
kWh
$202
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $7,650 - $7,650
85,379
kWh
- -
05 2.7232: Replace existing hvac unit with high efficiency model $586 $8,100 $537
5,990
kWh
$49
-
kW-mo/yr
-
TOTAL RECOMMENDED $133,643 $786,822 $106,524
1,188,330
kWh
$25,805
-
kW-mo/yr
$1,314
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs