| Assessment Year | 2006 |
|---|---|
| Principal Product | Lumber |
| NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 66 |
| Plant Area |
45,000
ft2
|
| Annual Production | 13,000
thousand feet
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $238,420 | 309,150 |
kWh
|
$0.77 |
| Electricity Demand | $36,248 | 9,062 |
kW-mo/yr
|
$4.00 |
| Electricity Fees | $4,608 | - |
|
- |
| Natural Gas | $31,972 | 50,500 |
MMBtu
|
$0.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $411,422 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,457 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $399,965 | $2,750,000 |
$238,420
11,137,500
kWh
|
$36,248
-
kW-mo/yr
|
$4,607 | $120,690 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,357 | $7,875 |
$4,477
56,026
kWh
|
$800
-
kW-mo/yr
|
$80 | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,962 | $156 |
$2,918
36,509
kWh
|
- | $44 | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,297 | $2,981 |
$1,995
24,964
kWh
|
$268
-
kW-mo/yr
|
$34 | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $841 | $3,593 |
$705
8,817
kWh
|
$124
-
kW-mo/yr
|
$12 | - | |
| TOTAL RECOMMENDED | $411,422 | $2,764,605 |
$248,515
11,263,816
kWh
|
$37,440
-
kW-mo/yr
|
$4,777 | $120,690 | ||
| TOTAL IMPLEMENTED | $11,457 | $14,605 |
$10,095
126,316
kWh
|
$1,192
-
kW-mo/yr
|
$170 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs