ITAC Assessment: MS0309
ITAC logo
ITAC Assessment: MS0309
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Lumber
NAICS 321912: Cut Stock, Resawing Lumber, and Planing
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area 45,000
ft2
Annual Production 13,000
thousand feet
Production Hrs. Annual 4,500
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $238,420 309,150
kWh
Electricity Demand $36,248 9,062
kW-mo/yr
Electricity Fees $4,608 -
Natural Gas $31,972 50,500
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $411,422 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,457

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings By-product Production Savings
01 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat $399,965 $2,750,000 $238,420
11,137,500
kWh
$36,248
-
kW-mo/yr
$4,607 $120,690
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,357 $7,875 $4,477
56,026
kWh
$800
-
kW-mo/yr
$80 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,962 $156 $2,918
36,509
kWh
- $44 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,297 $2,981 $1,995
24,964
kWh
$268
-
kW-mo/yr
$34 -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $841 $3,593 $705
8,817
kWh
$124
-
kW-mo/yr
$12 -
TOTAL RECOMMENDED $411,422 $2,764,605 $248,515
11,263,816
kWh
$37,440
-
kW-mo/yr
$4,777 $120,690
TOTAL IMPLEMENTED $11,457 $14,605 $10,095
126,316
kWh
$1,192
-
kW-mo/yr
$170 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs