ITAC Assessment: MO0270
ITAC logo
ITAC Assessment: MO0270
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Optical Lenses and Fused Multifocals
NAICS
n/a
SIC 3851: Ophthalmic Goods
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 40,000
ft2
Annual Production 850,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $293,641 5,643,611
kWh
Electricity Demand $34,716 1,406
kW-mo/yr
Electricity Fees $43,625 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $97,739 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,783

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $10,783 $36,941 $9,005
150,645
kWh
$1,778
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,802 $10,421 $4,012
67,116
kWh
$790
-
kW-mo/yr
- -
03 2.2437: Recover waste heat from equipment $235 $53 $210
3,517
kWh
$25
-
kW-mo/yr
- -
04 3.1175: Use a different or recycled raw material $720 $1,800 - - $720
-
lb
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $76,792 - - - - $76,792
06 2.3133: Consider three or four days around-the-clock operation rather than one or two shifts per day $4,407 - - - - $4,407
TOTAL RECOMMENDED $97,739 $49,215 $13,227
221,278
kWh
$2,593
-
kW-mo/yr
$720
-
lb
$81,199
TOTAL IMPLEMENTED $10,783 $36,941 $9,005
150,645
kWh
$1,778
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs