Assessment Year | 1998 |
---|---|
Principal Product | Beef Patty Processing and Packets Products |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
90,000
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $263,656 | 5,395,076 |
kWh
|
$0.049 |
Electricity Demand | $29,341 | 1,273 |
kW-mo/yr
|
$23.05 |
Electricity Fees | $33,725 | - |
|
- |
Natural Gas | $14,663 | 2,908 |
MMBtu
|
$5.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,690,908 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.441: Install automatic packing equipment | $440,000 | $950,000 | n/a | - | - | - | $440,000 |
02 | 4.432: Cross-train personnel to avoid lost time | $22,725 | $25,000 | n/a | - | - | - | $22,725 |
03 | 4.514: Re-arrange equipment layout to reduce handling costs | $9,450 | $15,000 | n/a | - | - | - | $9,450 |
04 | 4.611: Begin a practice of predictive / preventative maintenance | $5,155 | $3,700 | n/a | - | - | - | $5,155 |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,777 | $3,872 | n/a |
$1,565
28,429
kWh
|
$212
-
kW-mo/yr
|
- | - |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $116 | $207 | n/a |
$111
2,052
kWh
|
$5
-
kW-mo/yr
|
- | - |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $661 | $80 | n/a |
$620
11,137
kWh
|
$41
-
kW-mo/yr
|
- | - |
08 | 2.4133: Use most efficient type of electric motors | $10,841 | $13,179 | n/a |
$10,189
184,936
kWh
|
$652
-
kW-mo/yr
|
- | - |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $383 | - | n/a |
$360
6,448
kWh
|
$23
-
kW-mo/yr
|
- | - |
10 | 4.212: Adopt in-house material generation | $1,024,800 | $2,968,600 | n/a | - | - |
$1,024,800
-
lb
|
- |
11 | 3.1163: Use plastic pallets instead of wood | $175,000 | $56,250 | n/a | - | - |
$175,000
-
lb
|
- |
TOTAL RECOMMENDED | $1,690,908 | $4,035,888 |
$12,845
233,002
kWh
|
$933
-
kW-mo/yr
|
$1,199,800
-
lb
|
$477,330 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs