ITAC Assessment: MI0410
ITAC logo
ITAC Assessment: MI0410
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Plants
NAICS 311999: All Other Miscellaneous Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 219,200
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,151 936,720
kWh
Electricity Demand $46,598 3,906
kW-mo/yr
Electricity Fees $12,206 -
Fuel Oil #2 $1,805 77
MMBtu
TOTAL YEARLY COSTS $121,760
RECOMMENDED SAVINGS* $37,936 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,018

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7221: Lower temperature during the winter season and vice-versa $11,438 $580 $9,136
140,551
kWh
$2,302
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $7,151 $7,280 $5,719
87,984
kWh
$1,432
-
kW-mo/yr
-
03 2.3192: Use fossil fuel powered generator during peak demand periods $5,890 $80 - - $5,890
04 2.9112: Use solar heat to heat water $3,955 $18,399 $3,955
60,842
kWh
- -
05 2.4313: Provide proper maintenance of motor driven equipment $3,575 $597 $2,859
43,992
kWh
$716
-
kW-mo/yr
-
06 2.6218: Turn off equipment when not in use $2,493 $140 $2,493
38,359
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,361 $10,695 $1,216
18,711
kWh
$1,145
-
kW-mo/yr
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,073 $2,150 $858
13,198
kWh
$215
-
kW-mo/yr
-
TOTAL RECOMMENDED $37,936 $39,921 $26,236
403,637
kWh
$5,810
-
kW-mo/yr
$5,890
TOTAL IMPLEMENTED $27,018 $19,292 $21,423
329,597
kWh
$5,595
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs