ITAC Assessment: MI0345
ITAC logo
ITAC Assessment: MI0345
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Processed Meat
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 29,000
ft2
Annual Production 1,280,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) Puerto Rico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,446 318,780
kWh
Electricity Demand $11,700 1,033
kW-mo/yr
Electricity Fees $2,529 -
LPG $14,329 712
MMBtu
Fuel Oil #2 $35,949 1,459
MMBtu
TOTAL YEARLY COSTS $122,953
RECOMMENDED SAVINGS* $22,933 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,928

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings
01 2.6218: Turn off equipment when not in use $7,969 $3,100 $7,969
43,545
kWh
- - -
02 2.7425: Clean or color roof to reduce solar load $6,837 $3,204 $5,786
31,617
kWh
$1,051
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,576 $3,443 $2,259
12,345
kWh
$317
-
kW-mo/yr
- -
04 2.2414: Use waste heat from hot flue gases to preheat $1,410 $1,982 - - - $1,410
-
MMBtu
05 2.7135: Install occupancy sensors $1,380 $540 $1,153
6,303
kWh
$227
-
kW-mo/yr
- -
06 2.9112: Use solar heat to heat water $1,166 $2,755 $883
4,824
kWh
$283
-
kW-mo/yr
- -
07 2.3212: Optimize plant power factor $810 $2,138 - - $810 -
08 2.1233: Analyze flue gas for proper air/fuel ratio $785 $1,560 - - - $785
-
MMBtu
TOTAL RECOMMENDED $22,933 $18,722 $18,050
98,634
kWh
$1,878
-
kW-mo/yr
$810 $2,195
-
MMBtu
TOTAL IMPLEMENTED $19,928 $13,042 $18,050
98,634
kWh
$1,878
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs