| Assessment Year | 2018 |
|---|---|
| Principal Product | Processed Meat |
| NAICS | 311612: Meat Processed from Carcasses |
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $1 M to 5M |
| # of Employees | 25 |
| Plant Area |
29,000
ft2
|
| Annual Production | 1,280,000
lb
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Puerto Rico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $58,446 | 318,780 |
kWh
|
$0.18 |
| Electricity Demand | $11,700 | 1,033 |
kW-mo/yr
|
$11.33 |
| Electricity Fees | $2,529 | - |
|
- |
| LPG | $14,329 | 712 |
MMBtu
|
$20.13 |
| Fuel Oil #2 | $35,949 | 1,459 |
MMBtu
|
$24.64 |
| TOTAL YEARLY COSTS | $122,953 | |||
| RECOMMENDED SAVINGS* | $22,933 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,928 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $7,969 | $3,100 |
$7,969
43,545
kWh
|
- | - | - | |
| 02 | 2.7425: Clean or color roof to reduce solar load | $6,837 | $3,204 |
$5,786
31,617
kWh
|
$1,051
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,576 | $3,443 |
$2,259
12,345
kWh
|
$317
-
kW-mo/yr
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $1,410 | $1,982 | - | - | - |
$1,410
-
MMBtu
|
|
| 05 | 2.7135: Install occupancy sensors | $1,380 | $540 |
$1,153
6,303
kWh
|
$227
-
kW-mo/yr
|
- | - | |
| 06 | 2.9112: Use solar heat to heat water | $1,166 | $2,755 |
$883
4,824
kWh
|
$283
-
kW-mo/yr
|
- | - | |
| 07 | 2.3212: Optimize plant power factor | $810 | $2,138 | - | - | $810 | - | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $785 | $1,560 | - | - | - |
$785
-
MMBtu
|
|
| TOTAL RECOMMENDED | $22,933 | $18,722 |
$18,050
98,634
kWh
|
$1,878
-
kW-mo/yr
|
$810 |
$2,195
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,928 | $13,042 |
$18,050
98,634
kWh
|
$1,878
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs