ITAC Assessment: MI0094
ITAC logo
ITAC Assessment: MI0094
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Electrical Cables
NAICS 335931: Current-Carrying Wiring Device Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 106,000
ft2
Annual Production 1,400,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,355 1,498,920
kWh
Electricity Demand $33,081 4,174
kW-mo/yr
Electricity Fees $13,103 -
LPG $14,127 759
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $260,429 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $257,497

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.8114: Change rate schedules or other changes in utility service $24,368 $2,300 $24,368
415,009
kWh
- - - - -
02 4.123: Reduce defects by reducing product tipping $95,473 $150 - - - - $(-150.0) $95,623
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $(-177.0) $590 $1,903
36,215
kWh
- $(-2,080.0) - - -
04 2.6218: Turn off equipment when not in use $9,418 $92 - $9,418
-
MMBtu
- - - -
05 4.652: Replace existing equipment with more suitable substitutes $1,547 - - $640
-
MMBtu
- - - $907
06 4.321: Optimize production lot sizes and inventories $1,385 - - - - - - $1,385
07 4.621: Use fixtures to reduce machine changeout times $11,093 $2,056 - - - - - $11,093
08 4.513: Re-arrange equipment layout to reduce labor costs $69,699 $5,966 - - - - - $69,699
09 4.431: Train operators for maximum operating efficiency $47,623 $4,110 $316
6,002
kWh
- - $(-5,000.0) - $52,307
TOTAL RECOMMENDED $260,429 $15,264 $26,587
457,226
kWh
$10,058
-
MMBtu
$(-2,080.0) $(-5,000.0) $(-150.0) $231,014
TOTAL IMPLEMENTED $257,497 $15,264 $26,587
457,226
kWh
$9,418
-
MMBtu
$(-2,080.0) $(-5,000.0) $(-150.0) $228,722
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs