Assessment Year | 1998 |
---|---|
Principal Product | shoes |
NAICS |
n/a
|
SIC | 3144: Women's Footwear, Except Athletic |
Sales Range | $1 M to 5M |
# of Employees | 62 |
Plant Area |
25,000
ft2
|
Annual Production | 72,000
units
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $20,834 | 281,653 |
kWh
|
$0.074 |
Electricity Demand | $14,796 | 1,710 |
kW-mo/yr
|
$8.65 |
Electricity Fees | $(-1,921.0) | - |
|
- |
Natural Gas | $5,143 | 630 |
MMBtu
|
$8.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,823 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,500 | $33,500 |
$14,200
203,107
kWh
|
$7,320
-
kW-mo/yr
|
$(-7,020.0)
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,816 | $8,713 |
$1,913
27,257
kWh
|
$903
-
kW-mo/yr
|
- | - | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,532 | - |
$1,013
14,361
kWh
|
$519
-
kW-mo/yr
|
- | - | |
04 | 2.4131: Size electric motors for peak operating efficiency | $810 | $1,000 |
$367
5,275
kWh
|
$443
-
kW-mo/yr
|
- | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $594 | $550 |
$252
3,517
kWh
|
$467
-
kW-mo/yr
|
$(-125.0)
-
MMBtu
|
- | |
06 | 2.1113: Reduce combustion air flow to optimum | $370 | $400 | - | - |
$370
-
MMBtu
|
- | |
07 | 2.2511: Insulate bare equipment | $396 | $858 |
$396
5,569
kWh
|
- | - | - | |
08 | 2.8121: Apply for tax-free status for energy purchases | $827 | - | - | - | - | $827 | |
TOTAL RECOMMENDED | $21,845 | $45,021 |
$18,141
259,086
kWh
|
$9,652
-
kW-mo/yr
|
$(-6,775.0)
-
MMBtu
|
$827 | ||
TOTAL IMPLEMENTED | $17,823 | $34,450 |
$15,465
220,985
kWh
|
$8,306
-
kW-mo/yr
|
$(-6,775.0)
-
MMBtu
|
$827 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs