Assessment Year | 1996 |
---|---|
Principal Product | Milk products |
NAICS |
n/a
|
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $50 M to 100M |
# of Employees | 125 |
Plant Area |
30,000
ft2
|
Annual Production | 20,000,000
Tgal
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $268,108 | 3,352,286 |
kWh
|
$0.080 |
Electricity Demand | $70,366 | 7,644 |
kW-mo/yr
|
$9.21 |
Electricity Fees | $3,291 | - |
|
- |
Natural Gas | $32,094 | 7,748 |
MMBtu
|
$4.14 |
Fuel Oil #4 | $11,431 | 3,415 |
MMBtu
|
$3.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,927 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,557 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,951 | $17,121 |
$8,639
123,388
kWh
|
$2,312
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,006 | $1,023 |
$2,095
26,084
kWh
|
$331
-
kW-mo/yr
|
$(-327.0)
-
MMBtu
|
$(-93.0)
-
MMBtu
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $2,367 | $2,500 | - | - |
$1,839
-
MMBtu
|
$528
-
MMBtu
|
- | - | - | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $263 | - | - | - | - | - | - | - | - | $263 | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $15,370 | $14,700 | - | - | - | - |
$(-310.0)
-
Tgal
|
$15,680
-
gal
|
- | - | |
06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $12,262 | - | - | - | - | - | - | - |
$12,262
-
lb
|
- | |
07 | 3.4154: Eliminate leaks in water lines and valves | $5,658 | $400 | - | - |
$2,090
-
MMBtu
|
$600
-
MMBtu
|
$2,415
-
Tgal
|
$553
-
gal
|
- | - | |
08 | 3.4154: Eliminate leaks in water lines and valves | $1,050 | $1,330 | - | - |
$374
-
MMBtu
|
$107
-
MMBtu
|
$463
-
Tgal
|
$106
-
gal
|
- | - | |
TOTAL RECOMMENDED | $49,927 | $37,074 |
$10,734
149,472
kWh
|
$2,643
-
kW-mo/yr
|
$3,976
-
MMBtu
|
$1,142
-
MMBtu
|
$2,568
-
Tgal
|
$16,339
-
gal
|
$12,262
-
lb
|
$263 | ||
TOTAL IMPLEMENTED | $34,557 | $22,374 |
$10,734
149,472
kWh
|
$2,643
-
kW-mo/yr
|
$3,976
-
MMBtu
|
$1,142
-
MMBtu
|
$2,878
-
Tgal
|
$659
-
gal
|
$12,262
-
lb
|
$263 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs