ITAC Assessment: ME0180
ITAC logo
ITAC Assessment: ME0180
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Milk products
NAICS
n/a
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $50
M
to 100
M
# of Employees 125
Plant Area 30,000
ft2
Annual Production 20,000,000
Tgal
Production Hrs. Annual 6,240
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $268,108 3,352,286
kWh
Electricity Demand $70,366 7,644
kW-mo/yr
Electricity Fees $3,291 -
Natural Gas $32,094 7,748
MMBtu
Fuel Oil #4 $11,431 3,415
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,927 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,557

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #4 Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,951 $17,121 $8,639
123,388
kWh
$2,312
-
kW-mo/yr
- - - - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,006 $1,023 $2,095
26,084
kWh
$331
-
kW-mo/yr
$(-327.0)
-
MMBtu
$(-93.0)
-
MMBtu
- - - -
03 2.2511: Insulate bare equipment $2,367 $2,500 - - $1,839
-
MMBtu
$528
-
MMBtu
- - - -
04 2.8121: Apply for tax-free status for energy purchases $263 - - - - - - - - $263
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $15,370 $14,700 - - - - $(-310.0)
-
Tgal
$15,680
-
gal
- -
06 3.5212: Regrind, reuse, or sell scrap plastic parts $12,262 - - - - - - - $12,262
-
lb
-
07 3.4154: Eliminate leaks in water lines and valves $5,658 $400 - - $2,090
-
MMBtu
$600
-
MMBtu
$2,415
-
Tgal
$553
-
gal
- -
08 3.4154: Eliminate leaks in water lines and valves $1,050 $1,330 - - $374
-
MMBtu
$107
-
MMBtu
$463
-
Tgal
$106
-
gal
- -
TOTAL RECOMMENDED $49,927 $37,074 $10,734
149,472
kWh
$2,643
-
kW-mo/yr
$3,976
-
MMBtu
$1,142
-
MMBtu
$2,568
-
Tgal
$16,339
-
gal
$12,262
-
lb
$263
TOTAL IMPLEMENTED $34,557 $22,374 $10,734
149,472
kWh
$2,643
-
kW-mo/yr
$3,976
-
MMBtu
$1,142
-
MMBtu
$2,878
-
Tgal
$659
-
gal
$12,262
-
lb
$263
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #4 Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs