| Assessment Year | 1994 |
|---|---|
| Principal Product | Shoes |
| NAICS |
n/a
|
| SIC | 3143: Men's Footwear, Except Athletic |
| Sales Range | $5 M to 10M |
| # of Employees | 300 |
| Plant Area |
60,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $128,786 | 1,106,975 |
kWh
|
$0.12 |
| Fuel Oil #6 | $23,772 | 7,048 |
MMBtu
|
$3.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,005 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,107 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $390 | $450 |
$390
3,224
kWh
|
- | |
| 02 | 2.2136: Install / repair insulation on steam lines | $817 | $350 | - |
$817
-
MMBtu
|
|
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,700 | $4,000 |
$5,700
48,945
kWh
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $760 | $600 |
$760
6,448
kWh
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,600 | $5,300 |
$2,600
22,274
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,146 | $500 |
$1,146
9,965
kWh
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,900 | $600 |
$1,900
16,413
kWh
|
- | |
| 08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $692 | - |
$692
5,862
kWh
|
- | |
| TOTAL RECOMMENDED | $14,005 | $11,800 |
$13,188
113,131
kWh
|
$817
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,107 | $1,400 |
$2,290
19,637
kWh
|
$817
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs