| Assessment Year | 2012 |
|---|---|
| Principal Product | Motors and Motor Controls |
| NAICS | 335312: Motor and Generator Manufacturing |
| SIC | 3621: Motors and Generators |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
140,000
ft2
|
| Annual Production | 60
pieces
|
| Production Hrs. Annual | 2,860
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $165,914 | 1,533,624 |
kWh
|
$0.11 |
| Electricity Demand | $91,660 | 6,513 |
kW-mo/yr
|
$14.07 |
| Electricity Fees | $4,659 | - |
|
- |
| Natural Gas | $72,034 | 6,183 |
MMBtu
|
$11.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,098 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,178 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $19,479 | $19,600 |
$19,479
180,032
kWh
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,681 | $23,000 |
$13,925
128,700
kWh
|
$(-6,244.0)
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,178 | $7,500 |
$4,178
38,610
kWh
|
- | |
| 04 | 2.7135: Install occupancy sensors | $760 | $1,600 |
$760
7,021
kWh
|
- | |
| TOTAL RECOMMENDED | $32,098 | $51,700 |
$38,342
354,363
kWh
|
$(-6,244.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,178 | $7,500 |
$4,178
38,610
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs