ITAC Assessment: MA0862
ITAC logo
ITAC Assessment: MA0862
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Municipal Wastewater Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 7
Plant Area 215,000
ft2
Annual Production 640,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $351,462 2,530,400
kWh
Electricity Demand $41,784 4,760
kW-mo/yr
Natural Gas $33,037 1,933
MMBtu
TOTAL YEARLY COSTS $426,283
RECOMMENDED SAVINGS* $105,123 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,262 $30,900 $28,769
206,971
kWh
$2,493
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $29,114 $20,600 $26,797
192,782
kWh
$2,317
-
kW-mo/yr
- -
03 3.1191: Change procedures / equipment / operating conditions $24,241 $55,000 $22,310
160,500
kWh
$1,931
-
kW-mo/yr
- -
04 2.9114: Use solar heat to make electricty $11,416 $78,169 $6,806
48,962
kWh
$1,159
-
kW-mo/yr
- $3,451
05 2.7234: Use heat pump for space conditioning $4,461 $14,400 $4,110
29,565
kWh
$351
-
kW-mo/yr
- -
06 2.7224: Reduce space conditioning during non-working hours $3,059 $800 - - $3,059
-
MMBtu
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,570 $2,160 $1,210
8,704
kWh
$360
-
kW-mo/yr
- -
TOTAL RECOMMENDED $105,123 $202,029 $90,002
647,484
kWh
$8,611
-
kW-mo/yr
$3,059
-
MMBtu
$3,451
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs