Assessment Year | 2016 |
---|---|
Principal Product | Computer Electronics and Printed Circuit Boards |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
39,880
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 4,743
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $457,365 | 3,379,000 |
kWh
|
$0.14 |
Electricity Demand | $33,042 | 8,429 |
kW-mo/yr
|
$3.92 |
Electricity Fees | $2,554 | - |
|
- |
Natural Gas | $38,776 | 3,805 |
MMBtu
|
$10.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,538 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,899 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,102 | $6,500 |
$8,102
59,836
kWh
|
- | - | |
02 | 2.7135: Install occupancy sensors | $6,277 | $2,320 |
$6,277
46,363
kWh
|
- | - | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,797 | $7,000 |
$3,797
28,045
kWh
|
- | - | |
04 | 2.7314: Reduce ventilation air | $1,278 | $1,000 |
$616
4,546
kWh
|
- |
$662
-
MMBtu
|
|
05 | 2.2531: Re-size charging openings or add movable cover or door | $1,508 | $10,800 | - | - |
$1,508
-
MMBtu
|
|
06 | 2.3212: Optimize plant power factor | $576 | $1,392 | - |
$576
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $21,538 | $29,012 |
$18,792
138,790
kWh
|
$576
-
kW-mo/yr
|
$2,170
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,899 | $13,500 |
$11,899
87,881
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs