Assessment Year | 2014 |
---|---|
Principal Product | Miniature Precision Zinc and Plastic Parts |
NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
SIC | 3364: Nonferrous Die-Castings, Except Aluminum |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
24,000
ft2
|
Annual Production | 390,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,153 | 773,760 |
kWh
|
$0.091 |
Electricity Demand | $8,504 | 2,542 |
kW-mo/yr
|
$3.35 |
Electricity Fees | $9,741 | - |
|
- |
Natural Gas | $6,004 | 476 |
MMBtu
|
$12.61 |
LPG | $3,679 | 108 |
MMBtu
|
$34.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,663 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $338 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,242 | $53,572 |
$20,246
223,222
kWh
|
$1,045
-
kW-mo/yr
|
$(-8,049.0)
-
MMBtu
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,069 | $15,975 |
$5,069
55,889
kWh
|
- | - | - | |
03 | 2.1331: Burn a less expensive grade of fuel | $2,667 | $2,565 | - | - |
$(-1,012.0)
-
MMBtu
|
$3,679
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $2,594 | $2,614 |
$2,594
28,596
kWh
|
- | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $753 | $2,210 |
$753
8,310
kWh
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $338 | $300 |
$338
3,722
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $24,663 | $77,236 |
$29,000
319,739
kWh
|
$1,045
-
kW-mo/yr
|
$(-9,061.0)
-
MMBtu
|
$3,679
-
MMBtu
|
||
TOTAL IMPLEMENTED | $338 | $300 |
$338
3,722
kWh
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs