| Assessment Year | 2014 |
|---|---|
| Principal Product | Standard and Special cuttingTools |
| NAICS | 333517: Machine Tool Manufacturing |
| SIC | 3541: Machine Tools, Metal Cutting Types |
| Sales Range | $5 M to 10M |
| # of Employees | 44 |
| Plant Area |
55,000
ft2
|
| Annual Production | 4,160
pieces
|
| Production Hrs. Annual | 4,080
hrs
|
| Location (State) | Vermont |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $81,470 | 1,140,585 |
kWh
|
$0.071 |
| Electricity Demand | $57,350 | 6,681 |
kW-mo/yr
|
$8.58 |
| Electricity Fees | $23,366 | - |
|
- |
| LPG | $26,391 | 1,507 |
MMBtu
|
$17.51 |
| Fuel Oil #4 | $41,251 | 1,874 |
MMBtu
|
$22.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,890 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,566 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #4 Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $16,512 | $25,775 | - |
$(-6,708.0)
-
MMBtu
|
$23,220
-
MMBtu
|
- | |
| 02 | 2.1224: Replace boiler | $10,114 | $30,450 | - |
$(-30,916.0)
-
MMBtu
|
$41,030
-
MMBtu
|
- | |
| 03 | 2.2628: Utilize a less expensive cooling method | $2,940 | $6,500 |
$(-1,636.0)
(-21,812)
kWh
|
- | - |
$4,576
-
Tgal
|
|
| 04 | 2.2136: Install / repair insulation on steam lines | $324 | $350 | - | - |
$324
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $29,890 | $63,075 |
$(-1,636.0)
(-21,812)
kWh
|
$(-37,624.0)
-
MMBtu
|
$64,574
-
MMBtu
|
$4,576
-
Tgal
|
||
| TOTAL IMPLEMENTED | $29,566 | $62,725 |
$(-1,636.0)
(-21,812)
kWh
|
$(-37,624.0)
-
MMBtu
|
$64,250
-
MMBtu
|
$4,576
-
Tgal
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs