| Assessment Year | 2013 |
|---|---|
| Principal Product | Mica insullation products |
| NAICS | 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing |
| SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
60,000
ft2
|
| Annual Production | 1,160,000
pieces
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | Vermont |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $249,791 | 3,617,378 |
kWh
|
$0.069 |
| Electricity Demand | $66,313 | 6,936 |
kW-mo/yr
|
$9.56 |
| Electricity Fees | $70,200 | - |
|
- |
| LPG | $248,233 | 18,205 |
MMBtu
|
$13.64 |
| Fuel Oil #6 | $299,105 | 17,164 |
MMBtu
|
$17.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $105,189 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $92,729 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #6 Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1331: Burn a less expensive grade of fuel | $64,988 | $67,000 | - | - |
$(-234,117.0)
-
MMBtu
|
$299,105
-
MMBtu
|
|
| 02 | 2.2136: Install / repair insulation on steam lines | $9,831 | $5,568 | - | - | - |
$9,831
-
MMBtu
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,362 | $13,800 |
$5,362
77,834
kWh
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $4,919 | $12,300 |
$4,919
71,393
kWh
|
- | - | - | |
| 05 | 2.2511: Insulate bare equipment | $4,187 | $7,500 | - | - |
$4,187
-
MMBtu
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,354 | $9,300 |
$149
2,160
kWh
|
- |
$3,205
-
MMBtu
|
- | |
| 07 | 2.3212: Optimize plant power factor | $11,188 | $13,500 | - |
$11,188
-
kW-mo/yr
|
- | - | |
| 08 | 2.6213: Turn off steam / hot water lines leading to space heating units | $1,360 | $150 | - | - | - |
$1,360
-
MMBtu
|
|
| TOTAL RECOMMENDED | $105,189 | $129,118 |
$10,430
151,387
kWh
|
$11,188
-
kW-mo/yr
|
$(-226,725.0)
-
MMBtu
|
$310,296
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $92,729 | $100,018 |
$5,362
77,834
kWh
|
$11,188
-
kW-mo/yr
|
$(-234,117.0)
-
MMBtu
|
$310,296
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #6 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs