Assessment Year | 2013 |
---|---|
Principal Product | coated wires and cables |
NAICS | 335929: Other Communication and Energy Wire Manufacturing |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
82,000
ft2
|
Annual Production | 11,000
thousand feet
|
Production Hrs. Annual | 6,300
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $161,336 | 1,595,400 |
kWh
|
$0.10 |
Electricity Demand | $23,961 | 6,314 |
kW-mo/yr
|
$3.79 |
Electricity Fees | $12,152 | - |
|
- |
Natural Gas | $6,905 | 631 |
MMBtu
|
$10.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,022 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,467 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $8,642 | $200 | - | - | $8,642 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,284 | $19,400 |
$7,700
78,580
kWh
|
$584
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,053 | $2,800 |
$6,053
61,772
kWh
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,037 | $8,350 |
$6,037
61,612
kWh
|
- | - | |
05 | 2.3212: Optimize plant power factor | $3,939 | $13,700 | - |
$3,939
-
kW-mo/yr
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $2,632 | $4,231 |
$2,632
26,867
kWh
|
- | - | |
07 | 2.8123: Pay utility bills on time | $1,191 | $500 | - | - | $1,191 | |
08 | 2.2136: Install / repair insulation on steam lines | $244 | $497 |
$244
2,488
kWh
|
- | - | |
TOTAL RECOMMENDED | $37,022 | $49,678 |
$22,666
231,319
kWh
|
$4,523
-
kW-mo/yr
|
$9,833 | ||
TOTAL IMPLEMENTED | $19,467 | $36,400 |
$13,753
140,352
kWh
|
$4,523
-
kW-mo/yr
|
$1,191 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs