Assessment Year | 1994 |
---|---|
Principal Product | Aluminum components |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
79,862
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,790 | 895,369 |
kWh
|
$0.12 |
Natural Gas | $61,768 | 12,833 |
MMBtu
|
$4.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,501 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $10,409 | $15,400 | - |
$10,409
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,461 | $30 |
$3,461
29,015
kWh
|
- | |
03 | 2.2531: Re-size charging openings or add movable cover or door | $3,339 | $5,980 | - |
$3,339
-
MMBtu
|
|
04 | 2.2122: Install / repair insulation on condensate lines | $795 | $816 | - |
$795
-
MMBtu
|
|
05 | 2.2437: Recover waste heat from equipment | $60 | $594 | - |
$60
-
MMBtu
|
|
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $245 | - |
$245
2,052
kWh
|
- | |
TOTAL RECOMMENDED | $18,309 | $22,820 |
$3,706
31,067
kWh
|
$14,603
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,501 | $846 |
$3,706
31,067
kWh
|
$795
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs