Assessment Year | 1989 |
---|---|
Principal Product | AEROSOL & STICK SOLIDS |
NAICS |
n/a
|
SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
Sales Range | $10 M to 50M |
# of Employees | 450 |
Plant Area |
n/a
|
Annual Production | 110,000
Tgal
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $495,371 | 5,720,399 |
kWh
|
$0.087 |
LPG | $1,770 | 152 |
MMBtu
|
$11.64 |
Fuel Oil #6 | $128,935 | 50,981 |
MMBtu
|
$2.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $335 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $335 | $703 | - | - |
$335
-
MMBtu
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $476 | $1,254 |
$562
7,034
kWh
|
- |
$(-86.0)
-
MMBtu
|
- | |
03 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $30,146 | $123,000 |
$39,108
412,368
kWh
|
- |
$(-7,962.0)
-
MMBtu
|
$(-1,000.0) | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,375 | $3,000 |
$3,140
38,980
kWh
|
$(-1,765.0)
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $32,332 | $127,957 |
$42,810
458,382
kWh
|
$(-1,765.0)
-
MMBtu
|
$(-7,713.0)
-
MMBtu
|
$(-1,000.0) | ||
TOTAL IMPLEMENTED | $335 | $703 | - | - |
$335
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs