ITAC Assessment: MA0002
ITAC logo
ITAC Assessment: MA0002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product MOLDED PLASTIC ITEMS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $369,209 5,334,115
kWh
Fuel Oil #6 $25,220 3,952
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,732 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,782

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Fuel Oil #6 Savings
01 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $2,889 $200 $2,889
-
MMBtu
02 2.7221: Lower temperature during the winter season and vice-versa $3,893 - $3,893
-
MMBtu
03 2.2449: Recover heat from exhausted steam, hot air or hot water $13,950 $22,000 $13,950
-
MMBtu
TOTAL RECOMMENDED $20,732 $22,200 $20,732
-
MMBtu
TOTAL IMPLEMENTED $6,782 $200 $6,782
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs