ITAC Assessment: LT0024
ITAC logo
ITAC Assessment: LT0024
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product SHINGLES
NAICS
n/a
SIC 2952: Asphalt Felts and Coatings
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area
n/a
Annual Production 75
thousand feet
Production Hrs. Annual 2,250
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $152,862 2,674,091
kWh
Natural Gas $275,189 62,935
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,078 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,469

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,263 $642 $2,263
48,359
kWh
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $12,930 - - $13,530
-
MMBtu
$(-600.0)
03 2.1243: Use heat from boiler blowdown to preheat boiler feed water $4,160 $1,930 - $4,160
-
MMBtu
-
04 2.1213: Direct warmest air to combustion intake $836 - - $836
-
MMBtu
-
05 2.1131: Repair faulty insulation in furnaces, boilers, etc $2,010 $300 - $2,010
-
MMBtu
-
06 2.2136: Install / repair insulation on steam lines $3,430 $2,170 - $3,430
-
MMBtu
-
07 2.7121: Utilize daylight whenever possible in lieu of artificial light $449 $379 $405
4,982
kWh
- $44
TOTAL RECOMMENDED $26,078 $5,421 $2,668
53,341
kWh
$23,966
-
MMBtu
$(-556.0)
TOTAL IMPLEMENTED $21,469 $3,112 $2,263
48,359
kWh
$19,806
-
MMBtu
$(-600.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs