Assessment Year | 1985 |
---|---|
Principal Product | SHINGLES |
NAICS |
n/a
|
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
n/a
|
Annual Production | 75
thousand feet
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $152,862 | 2,674,091 |
kWh
|
$0.057 |
Natural Gas | $275,189 | 62,935 |
MMBtu
|
$4.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,078 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,469 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,263 | $642 |
$2,263
48,359
kWh
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $12,930 | - | - |
$13,530
-
MMBtu
|
$(-600.0) | |
03 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $4,160 | $1,930 | - |
$4,160
-
MMBtu
|
- | |
04 | 2.1213: Direct warmest air to combustion intake | $836 | - | - |
$836
-
MMBtu
|
- | |
05 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $2,010 | $300 | - |
$2,010
-
MMBtu
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $3,430 | $2,170 | - |
$3,430
-
MMBtu
|
- | |
07 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $449 | $379 |
$405
4,982
kWh
|
- | $44 | |
TOTAL RECOMMENDED | $26,078 | $5,421 |
$2,668
53,341
kWh
|
$23,966
-
MMBtu
|
$(-556.0) | ||
TOTAL IMPLEMENTED | $21,469 | $3,112 |
$2,263
48,359
kWh
|
$19,806
-
MMBtu
|
$(-600.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs