ITAC Assessment: LS2104
ITAC logo
ITAC Assessment: LS2104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Ready Mix Concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 32
Plant Area 146,813
ft2
Annual Production 120,000
units
Production Hrs. Annual 4,160
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $6,138 43,543
kWh
Natural Gas $912 118
MMBtu
Fuel Oil #1 $234,750 94,719
MMBtu
Waste Disposal Costs
Water Usage $8,200 5,422
Tgal
TOTAL YEARLY COSTS $250,000
RECOMMENDED SAVINGS* $15,463 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,597

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #1 Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,266 $180 $1,266
8,977
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $110 $25 $110
777
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $993 $380 $993
7,044
kWh
- -
04 2.8226: Increase efficiency of trucks $12,848 $5,150 - $173
-
MMBtu
$12,675
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $18 $23 $18
131
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $228 $300 $228
1,614
kWh
- -
TOTAL RECOMMENDED $15,463 $6,058 $2,615
18,543
kWh
$173
-
MMBtu
$12,675
TOTAL IMPLEMENTED $2,597 $885 $2,597
18,412
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #1 Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs