ITAC Assessment: LS0726
ITAC logo
ITAC Assessment: LS0726
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Office Building
NAICS 531120: Lessors of Nonresidential Buildings (except Miniwarehouses)
SIC 6512: Operators of Nonresidential Buildings
Sales Range less than $500
k
# of Employees 100
Plant Area 95,882
ft2
Annual Production 1
units
Production Hrs. Annual 3,120
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $136,077 1,816,200
kWh
Electricity Demand $56,231 6,348
kW-mo/yr
TOTAL YEARLY COSTS $192,308
RECOMMENDED SAVINGS* $44,397 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7423: Reduce heat gain by window tinting $21,059 $68,250 $21,059
280,794
kWh
-
02 2.7135: Install occupancy sensors $2,920 $22,000 $2,920
38,938
kWh
-
03 2.2622: Replace existing chiller with high efficiency model $20,418 $305,250 $14,040
187,200
kWh
$6,378
-
kW-mo/yr
TOTAL RECOMMENDED $44,397 $395,500 $38,019
506,932
kWh
$6,378
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs