Assessment Year | 2005 |
---|---|
Principal Product | bio-pesticide |
NAICS | 325320: Pesticide and Other Agricultural Chemical Manufacturing |
SIC | 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
105,000
ft2
|
Annual Production | 1,700,000
lb
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,184,986 | 11,092,617 |
kWh
|
$0.11 |
Electricity Demand | $288,318 | 22,692 |
kW-mo/yr
|
$12.71 |
Electricity Fees | $(-22,356.0) | - |
|
- |
Natural Gas | $520,060 | 94,682 |
MMBtu
|
$5.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $509,604 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $390,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $93,378 | $1,200 |
$80,100
759,351
kWh
|
$13,278
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $5,900 | $2,262 |
$5,061
47,963
kWh
|
$839
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,871 | $750 |
$3,320
31,472
kWh
|
$551
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $376 | - |
$305
2,488
kWh
|
$71
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $1,202 | $750 |
$1,031
8,420
kWh
|
$171
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2121: Increase amount of condensate returned | $67,226 | $100,000 | - | - |
$67,226
-
MMBtu
|
- | - | - | |
07 | 3.4154: Eliminate leaks in water lines and valves | $749 | $100 | - | - | - | - |
$749
-
Tgal
|
- | |
08 | 4.454: Modify startup/shutdown times | $101,277 | $1,000 | - | - | - | $101,277 | - | - | |
09 | 4.431: Train operators for maximum operating efficiency | $115,000 | $3,000 |
$10,000
110,000
kWh
|
- |
$5,000
-
MMBtu
|
- | - | $100,000 | |
10 | 4.513: Re-arrange equipment layout to reduce labor costs | $23,750 | $1,000 | - | - | - | - | - | $23,750 | |
11 | 4.122: Develop standard procedures to improve internal yields | $46,875 | $50,000 | - | - | - | - | - | $46,875 | |
12 | 4.122: Develop standard procedures to improve internal yields | $50,000 | $50,000 | - | - | - | - | - | $50,000 | |
TOTAL RECOMMENDED | $509,604 | $210,062 |
$99,817
959,694
kWh
|
$14,910
-
kW-mo/yr
|
$72,226
-
MMBtu
|
$101,277 |
$749
-
Tgal
|
$220,625 | ||
TOTAL IMPLEMENTED | $390,800 | $59,312 |
$98,481
948,786
kWh
|
$14,668
-
kW-mo/yr
|
$5,000
-
MMBtu
|
$101,277 |
$749
-
Tgal
|
$170,625 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs