Assessment Year | 2003 |
---|---|
Principal Product | Die Castings |
NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
SIC | 3363: Aluminum Die-Castings |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
22,000
ft2
|
Annual Production | 2,000,000
lb
|
Production Hrs. Annual | 3,875
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,375 | 1,799,070 |
kWh
|
$0.13 |
Electricity Demand | $63,120 | 4,800 |
kW-mo/yr
|
$13.15 |
Electricity Fees | $1,846 | - |
|
- |
Natural Gas | $98,568 | 18,890 |
MMBtu
|
$5.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $69,200 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,670 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,854 | $5,078 |
$2,327
17,939
kWh
|
$527
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,564 | - |
$2,055
16,445
kWh
|
$509
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $349 | $267 |
$272
2,172
kWh
|
$77
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,866 | $16,975 |
$4,808
38,565
kWh
|
$1,058
-
kW-mo/yr
|
- | - | |
05 | 2.1113: Reduce combustion air flow to optimum | $1,181 | $260 | - | - |
$1,181
-
MMBtu
|
- | |
06 | 2.2511: Insulate bare equipment | $1,079 | $120 | - | - |
$1,079
-
MMBtu
|
- | |
07 | 2.2437: Recover waste heat from equipment | $1,489 | $368 |
$901
7,212
kWh
|
$178
-
kW-mo/yr
|
$410
-
MMBtu
|
- | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $40,318 | $55,000 |
$39,396
330,214
kWh
|
$7,182
-
kW-mo/yr
|
$(-6,260.0)
-
MMBtu
|
- | |
09 | 4.431: Train operators for maximum operating efficiency | $13,500 | - | - | - | - | $13,500 | |
TOTAL RECOMMENDED | $69,200 | $78,068 |
$49,759
412,547
kWh
|
$9,531
-
kW-mo/yr
|
$(-3,590.0)
-
MMBtu
|
$13,500 | ||
TOTAL IMPLEMENTED | $2,670 | $628 |
$901
7,212
kWh
|
$178
-
kW-mo/yr
|
$1,591
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs